Latest news, Construction Update

Dec, 2022Construction

It’s been a busy time at Westbrook over the past few months. 

Key construction highlights and milestones include … 

Purchasers in Stage 54A will be excited to hear that civil construction works are now complete. Statement of Compliance has been achieved and lodged at the Titles Office

Stage 55 is also starting to take shape, as the road structure is now starting to be laid down

Over in Stage 45AC, civil construction is progressing well with sewer, drainage and kerb works now completed and titles expected 1st quarter 2023

Stage 49, drainage and sewer works are now underway and progressing well

The first layer of crushed rock for Stage 64 road structures is complete, along with kerb and channel works

 

 